Customized formwork and scaffolding solution from one source

The VARIOKIT tunnel formwork carriage has been designed so that trucks can pass through at any time without obstacles.

The VARIOKIT tunnel formwork carriage has been designed so that trucks can pass through at any time without obstacles.

Aug 5, 2013 | Nordhavnsvej Tunnel, Copenhagen, Denmark

Around 620 m of the extensive Nordhavnsvej infrastructure project runs underground. The twin-tubed, rectangular tunnel is being realized using the cut-and-cover method – the walls with Trio panelized formwork in advance followed by the slab formed with the Variokit tunnel formwork carriage. With the customized project solution, the construction team has achieved a three week cycle for the 25 m long concreting sections.

The "Nordhavnsvej – Vej- og Tunnelentreprise" project is the largest infrastructure project in Copenhagen of the past 50 year. The 1.65 km long route will eventually link Copenhagen´s northern port area with the Helsingør motorway. It runs through a very densely built urban area including depths of up to 22 m. One particular challenge regarding the execution was planning the course of the tunnel because the underground structure also crosses a very busy railway line. Completion of the complex connection of road and tunnel has been scheduled for autumn 2015.

The formwork solution for the tunnel

For the realization of the two tunnel tubes – each with 2 lanes – PERI planned a solution with wall formwork in advance and one slab formwork carriage which subsequently followed; this has been implemented in accordance with the requirements of the two joint venture partners.

The high demands placed on the design and concrete surfaces in the tunnel entrances have been fulfilled with a project-specific Vario GT 24 girder wall formwork solution. For the formwork elements of up to 12.80 m high and almost 25 m long, the construction team is using load-bearing, durable formwork girders of specially produced lengths.

The bottom slab and all other tunnel walls are concreted using the proven Trio panel formwork, in part single-sided against the bore pile wall of the sheet piling. The individual elements of the tried-and-tested formwork system are connected to form large-sized units which can then be moved extremely quickly by crane to the following casting segment.

For the subsequent construction of the 80 cm thick slabs, PERI engineers planned a total of 4 identical slab formwork carriages, each 13.50 m long, on the basis of the Variokit engineering construction kit. Two formwork carriages are coupled one behind the other per tube in order to concrete the 25 m long slab sections in each case. The highest priority for the design of the tunnel formwork carriage was to ensure simple and fast operations. For lifting and lowering, a hydraulic solution is therefore used so that adjustments can be made to the carriage in only one day for the next concreting section. The construction is then pulled to the following segment on crane rails by means of flanged wheels.

By bracing the formwork carriage using SLS heavy-duty spindles, a 4.00 m high and almost 4.30 wide access passage for site traffic could be realized. This was requested by the client so that the required materials can be delivered unimpeded. In order to construct the haunch on the support to the middle wall, a section of the slab formwork can be folded down by means of a spindle. To operate these spindles, the formwork carriage is equipped with cantilevered working platforms.

Thanks to the simple solution for the slab formwork carriage, the construction crew quickly became familiar with the operating procedure. The fact that well over 90 % of the carriage components are rentable system components also makes the solution extremely cost-effective. Special components are required in only a few sections – among other things for the stopend formwork. This is comprised of two formwork units arranged on top of each other which means that the required water stops between the concreting sections are easy to install and securely fixed in the correct position.

Access points and working scaffold – everything from one source

The stairways needed for the working areas and work scaffold are also supplied by Peri. As access to the slab formwork, the Alu 75 site staircase is used which is assembled with system components of the Peri Up Rosett Flex modular scaffolding. For the Copenhagen project, the 4-legged tower with staircase units in the same direction is mounted on the slab formwork carriage and the two are moved together to the next section each time.

The reinforcement scaffold is also assembled using system components of the modular scaffold. The scaffold units each consist of 3 bays with a length of 250 cm, and can be quickly moved to the next place of use using transportation wheels. This not only saves crane time but is also the only possible solution in those areas where the tunnel structure crosses the railway line. For fast and safe working operations, the scaffold – complete with integrated stair access and cantilevered brackets – is optimally adapted to match the available working area as well as the course of the concrete wall.

With an integrated system grid of 25 cm and 50 cm, the Peri Up Rosett Flex is extremely flexible; with the "gravity lock" and self-securing decks, every construction can be quickly assembled. A high level of safety is provided by the end-to-end guardrails and gap-free toe boards in a bright signal colour. The perforated surface of the decking also guarantees high slip resistance.

The "Nordhavnsvej – Vej- og Tunnelentreprise” project

The connection of the northern port area with the motorway through the densely built downtown district of Copenhagen is currently one of the largest construction projects in the city. The Nordhavnsvej – a combination of tunnel and an above-ground roadway – is scheduled for completion after a 4-years construction period with a total cost in the region of 2 billion Danish Kroner.

The road is designed to improve the connection to the port as well as ensuring that traffic noise levels for the residents of Copenhagen and the neighbouring town of Gentofte is greatly reduced. After the official opening in 2015, it is expected that around 15,000 cars will use the new connection per day.

PERI systems in use:
- PERI UP Rosett Flex Reinforcement
- PROKIT Safety System
- TRIO Panel Formwork
- VARIOKIT Tunnel Construction System

PERI was founded in 1969 and is today the leading provider of formwork and scaffolding systems. Along with the headquarters in Weissenhorn, Germany, the company has 52 international subsidiaries and 110 stock yards around the world. The company has over 5700 employees. 2012 revenues was 1,052 million Euros.

PERI GmbH
Editorial Office
P.O. Box 1264
89259 Weissenhorn
Germany

Phone: +49 (0) 7309.950-1191
Fax: +49 (0) 7309.951-1191
E-Mail: redaktion@peri.com
Web: www.peri.de

Re-prints are free of charge quoting "Source: PERI GmbH". Please send a copy to the PERI Editorial Office.

This release was published on openPR.

Permanent link to this press release:

Copy
Please set a link in the press area of your homepage to this press release on openPR. openPR disclaims liability for any content contained in this release.

You can edit or delete your press release Customized formwork and scaffolding solution from one source here

News-ID: 267392 • Views:

More Releases from PERI GmbH - Formwork, Scaffolding, Engineering

Formwork and scaffolding from one source for Berlin´s City Palace
Formwork and scaffolding from one source for Berlin´s City Palace
Sep 1, 2015 - "Humboldt Forum" City Palace, Berlin For the reconstruction of Berlin´s City Palace, PERI supplied cost-effective formwork and scaffolding solutions from one source. In addition to providing large quantities of wall, column and slab formwork with fast shuttering and moving times as well as flexibly used scaffolding materials, the on-site support provided by the PERI engineers ensured that all requirements could be fulfilled along with maintaining the tight
Construction time optimisation through comprehensive working safety and crane-independent climbing
Construction time optimisation through comprehensive working safety and crane-in …
Aug 3, 2015 - International Towers Sydney ITS, Barangaroo South, Sydney, Australia The new LPS climbing protection panel from PERI provides comprehensive working safety and saves valuable crane time thanks to the mobile climbing hydraulics. This has accelerated construction progress on the International Towers Sydney complex on Australia's east coast. With the ambitious Barangaroo Redevelopment Project, Sydney's city centre is being redefined in a westward direction. On the 22-hectare former container port
System-based project solution saves time and money
System-based project solution saves time and money
July 1, 2014 - Capitol Hill Station, Seattle, USA The formwork and scaffolding solution provided for the construction of the new subway station in Seattle was the result of competent engineering and a project-specific construction kit system. In addition to the widest possible use of rentable PERI system components, the optimized construction method in particular ensured significant time and cost savings. The length of Seattle´s metropolitan railway system (Light Rail) is currently
Formwork in every shape and dimension – even faster with the new CNC system
Formwork in every shape and dimension – even faster with the new CNC system
June 16, 2014 - Visions of architects take shape with PERI Planned, formed, concreted – it is actually hard to believe that this procedure could ever function trouble-free in some cases of present-day abstract concrete structures. In its pursuit of uniqueness, architecture is becoming more and more ambitious. Parallel to this, the requirements of construction companies are likewise increasing. PERI, however, is keeping pace with this trend: with individual formwork solutions,

All 5 Releases


More Releases for Copenhagen

Parkour photography workshops in London and Copenhagen
For the first time, Landmann Studios will be teaching two one-day parkour photography workshops in May, in London and Copenhagen. These workshops offer students the opportunity to shoot professional parkour athletes as they explore and interact with some of Europe’s most compelling architecture. LandmannStudios.com is a partnership between professional photographers/artists Andy Day and Diego Ferrari who between them have more than 30 years of photographic experience. Each day-long course
SGS to Attend EWEA 2012 in Copenhagen, Denmark
SGS will be attending EWEA 2012 in Copenhagen, Denmark as one of over 400 exhibitors. The services offered by SGS Renewable Energy will be presented throughout the exhibition at stand E-C79. EWEA 2012, held at the Bella Center, is Europe's premier wind energy event, combining a comprehensive, high-quality conference with a first class exhibition and incomparable networking opportunities. The four-day event provides an exciting opportunity for SGS to demonstrate its wide portfolio
Copenhagen Jewellery Fair: Innovative and trendy jewellery show
Events hellotrade is a regular updater of information on various events and conferences being held throughout the world. An accurate and apt piece of information is provided, which is useful for the visitors as well as participants having an urge to attend the event of their profile. The next upcoming event according to the listed events by eventshellotrade is Copenhagen Jewellery Fair. The fair is a must attend event and
eSciDoc Days 2010 in Copenhagen
FIZ Karlsruhe – Leibniz Institute for Information Infrastructure and Max Planck Society (MPG) invite to the third eSciDoc Days / presentation of eSciDoc infrastructure and applications / users tell about their experiences Karlsruhe, October 2010 – On November 16 and 17, 2010, the third eSciDoc Days will be held at the Royal Library in Copenhagen, Denmark. The event is held by FIZ Karlsruhe – Leibniz Institute for Information Infrastructure, and
Taiwan pledges support for Copenhagen resolutions
Though not a signatory to the United Nations Framework Convention on Climate Change (UNFCCC), as a member of the global village, Taiwan is willing to shoulder the common responsibility of protecting the planet’s natural environment, to support the recent Copenhagen Accord, to participate in UNFCCC-related activities, and to promote the reduction of carbon emissions, said Premier Wu Den-yih on April 8. He made the comments after receiving a briefing from
CoCoNet at EuroFinance 2009 in Copenhagen
At this year’s EuroFinance International Cash and Treasury Management in Copenhagen, Denmark, from 21–23 October 2009 with the innovative e-banking solution MULTIVERSA IFP International Finance Portal CoCoNet could give many answers to the open questions of treasury departments in international corporations. Among the most important topics experts for treasury and cash management discussed in this panel were the centralisation of the company-wide payment transactions, the direct SWIFTNet connectivity and the