Accelerated and safe construction with system components
16.11.2012 - De Rotterdam, Netherlands:The Rotterdam-based architect, Rem Koolhaas, has given his high-rise ensemble a huge "jolt" – and as a result has placed high demands on the construction work. Therefore, the supporting structure concept for realizing the cantilevers at a height of 86 m is an essential part of the comprehensive PERI overall solution.
De Rotterdam will be the largest building in the Netherlands – situated in the immediate vicinity to other architectural highlights such as the Erasmus Bridge by Van Berkel & Bos, the inclined high-rise building by Renzo Piano and the World Port Center by Sir Norman Foster. Once completed, the 150 m high multi-storey ensemble on Rotterdam´s Wilhelminapier peninsula on the south bank of the river Maas, will consist of three complex designed towers standing side by side and connected to each other. The West Tower has 45 residential levels, the 41-storey Central Tower is designed to be used as office facilities only whilst the 43 floors of the East Tower feature both office space as well as a hotel tract. In total, around 250 apartments, 280 hotel rooms and 60,000 m² of office space will be realised. The five-storey base section of the building has retail stores, restaurants, conference rooms and a fitness centre – as well as three parking decks on the ground floor and two basement levels.
A native of Rotterdam, renowned architect Rem Koolhaas has given his high-rise complex a huge "jolt" – shifting the upper half of the building to the side with a horizontal offset to the west and north. In so doing, at a height of 86 m, the 24th and 26th floors respectively along with the remaining upper storeys cantilever outwards up to 9 m. The construction site crew of Ed. Züblin AG, Stuttgart, has vast experience in realising high-rise buildings and the structural work is scheduled to be finished in early 2013 whilst the de Rotterdam CV project group plans to have all construction work completed by the end of the year. The rapid construction progress is supported through the use of comprehensive and ideally combined PERI system solutions. In particular, the supporting formwork solution for the cantilevered sections is an important component of the PERI overall concept.
Supporting structure with system
For realising the huge cantilevers at the great heights, PERI engineers developed a supporting formwork solution on the basis of the VARIOKIT engineering construction kit. For this, rentable system components are being used to a large extent, supplemented by a project-specific bracing construction. The flexible arrangement of the shear frames is carried out here whilst taking into account the respective geometry and loads of the structure as well as the range of mounting parts through to the masts of the tower cranes positioned in the building itself.
For dimensioning the beam heights in the West Tower, transferring the large loads from the 8.88 m cantilevers for two complete floors of the building and the low 3.52 m height of the storey below, had to be taken into consideration. For the Central and East Towers, a double-storey can be used for this purpose – here, the supporting formwork solution not only serves for transferring the loads from the cantilevers but also as a supporting structure between the floors.
Extensive PERI know-how is used to good effect especially in the beam extensions when the inherent load-bearing capacity of the building has been reached. The fact is that due to reasons of space, the shear frames cannot be simply retracted and disassembled within the storey itself without requiring direct crane support. For this purpose, the construction site crew is using the PERI lifting carriage that is normally used in connection with SKYTABLE large slab tables. The advantage of the PERI method – which was developed in and has been used for many years in North America – is that the shear frame is pulled horizontally from the building by means of a crane lift, a special chain block system and rear carriage.
Faster working through enhanced safety
With the RCS P climbing protection panel from PERI, the two topmost floors under construction are completely enclosed each time. As a result, site personnel are prevented from falling at all times and protected from strong winds at great heights – this means that forming operations are accelerated and work performance is greatly enhanced. Züblin requires only eight days for one complete standard floor.
Already during the planning phase, the geometrical changes of the towers were taken into consideration so that those protection panel units affected by the offset could be moved to other sections without requiring any extensive modification work. The RCS solution demonstrated its high level of flexibility in the areas close to the slab edge where anchoring was not an option. In this situation, too, the slab shoes are securely fixed and ensure fast climbing procedures due to the continuing rail guidance.
Crane-independent forming operations
With the SKYDECK panel slab formwork, floor slabs can be formed without the need of a crane. System components made of aluminum to facilitate the transport and, in particular, shuttering and striking can be carried out manually. The systematic and therefore easy to-understand assembly sequence accelerates the construction processes and also ensures that time requirements can be accurately estimated. In addition, through the use of the drophead and the possibility of early striking, this also reduces the amount of panels and main beams required on site.
For the floors in the base section, the systematic assembly sequence and the high degree of safety for each standard bay has already been achieved using the SKYDECK platforms and the cantilevered 375 SLT main beams, also at the slab edges. For the large supporting heights reaching over several floors, the construction crew have combined SKYDECK with the MULTIPROP load-bearing system. The lightweight aluminum individual props can be vertically connected to each other by means of the MULTIPROP connector – and joined together using MULTIPROP frames to form extremely stable shoring towers.
Pre-assembled units
De Rotterdam is encircled on all sides – longitudinally between the road and the Maas river as well as between two neighboring buildings at the ends. The narrow construction site therefore has very limited storage space. As a result, PERI supplied the RCS protection panel units and VARIOKIT shear frames already pre-assembled to the construction site. This means that these are lifted directly from the truck by crane and taken immediately to the designated place of use. This saves valuable crane time; in particular, no additional storage facilities and assembly area are required.
Contractor: Ed. Züblin AG, Direktion Stuttgart/Komplettbau Züblin Nederland B.V., Rotterdam
Architect: Rem Koolhaas, Office for Metropolitan Architecture (OMA), Rotterdam
Owner: De Rotterdam C.V. (MAB Development, Den Haag and OVG Projectontwikkeling, Rotterdam)
Field Service: PERI Stuttgart and PERI Weissenhorn, Germany
PERI Systems In Use
RCS P Climbing Protection Panel
SKYDECK Aluminium Panel Slab Formwork
PERI was founded in 1969 and is today the leading provider of formwork and scaffolding systems. Along with the headquarters in Weissenhorn, Germany, the company has 51 international subsidiaries and 110 stock yards around the world. The company has over 5700 employees. 2011 revenues was 976million Euros.
PERI GmbH
Editorial Office
P.O. Box 12 64
89259 Weissenhorn
Germany
Phone: +49 (0)7309.950-1191
Fax: +49 (0)7309.951-1191
www.peri.de
Re-prints are free of charge quoting "Source: PERI GmbH".
Please send a copy to the PERI Editorial Office.
This release was published on openPR.
Permanent link to this press release:
Copy
Please set a link in the press area of your homepage to this press release on openPR. openPR disclaims liability for any content contained in this release.
You can edit or delete your press release Accelerated and safe construction with system components here
News-ID: 243476 • Views: …
More Releases from PERI GmbH - Formwork, Scaffolding, Engineering

Formwork and scaffolding from one source for Berlin´s City Palace
Sep 1, 2015 - "Humboldt Forum" City Palace, Berlin
For the reconstruction of Berlin´s City Palace, PERI supplied cost-effective formwork and scaffolding solutions from one source. In addition to providing large quantities of wall, column and slab formwork with fast shuttering and moving times as well as flexibly used scaffolding materials, the on-site support provided by the PERI engineers ensured that all requirements could be fulfilled along with maintaining the tight…

Construction time optimisation through comprehensive working safety and crane-in …
Aug 3, 2015 - International Towers Sydney ITS, Barangaroo South, Sydney, Australia
The new LPS climbing protection panel from PERI provides comprehensive working safety and saves valuable crane time thanks to the mobile climbing hydraulics. This has accelerated construction progress on the International Towers Sydney complex on Australia's east coast.
With the ambitious Barangaroo Redevelopment Project, Sydney's city centre is being redefined in a westward direction. On the 22-hectare former container port…

System-based project solution saves time and money
July 1, 2014 - Capitol Hill Station, Seattle, USA
The formwork and scaffolding solution provided for the construction of the new subway station in Seattle was the result of competent engineering and a project-specific construction kit system. In addition to the widest possible use of rentable PERI system components, the optimized construction method in particular ensured significant time and cost savings.
The length of Seattle´s metropolitan railway system (Light Rail) is currently…

Formwork in every shape and dimension – even faster with the new CNC system
June 16, 2014 - Visions of architects take shape with PERI
Planned, formed, concreted – it is actually hard to believe that this procedure could ever function trouble-free in some cases of present-day abstract concrete structures. In its pursuit of uniqueness, architecture is becoming more and more ambitious. Parallel to this, the requirements of construction companies are likewise increasing. PERI, however, is keeping pace with this trend: with individual formwork solutions,…
More Releases for Rotterdam
@WORK Makelaardij: Top Real Estate Service in Rotterdam
When it comes to buying or investing in a property, investors must seek the help and guidance of real estate experts to make well-guided decisions. @WORK Makelaardij is a leading real estate company that focuses on providing trusted solutions for selling and buying a property. The real estate company's services are provided for investors and prospective homeowners. They have well-trained realtors on their team. Thus, they help clients post their…
@WORK Makelaardij: Leading Real Estate Service in Den Haag, Rotterdam, and Utrec …
@WORK Makelaardij, a leading real estate service company, provides trusted services in Den Haag, Rotterdam, and Utrecht.
Finding standard houses requires the expertise of highly experienced real estate professionals. @WORK Makelaardij is a reputable real estate service company that provides exceptional property selling and buying solutions. The real estate platform has been in the industry for years, helping investors and clients with their real estate needs. They specialize in the buying…
@Work Real Estate, A Leading Rotterdam Real Estate Agency
@Work Real Estate is a reliable company that offers brokerage services in the Netherlands.
@Work Real Estate, a leading brokerage service in the real estate industry, is celebrating over a decade of success in providing top-notch services to individuals and businesses looking to sell, buy, or rent properties. With a wide range of properties available, including houses, flats, warehouses, and offices, @Work Real Estate has become a go-to resource for those…
Bioenergy Market is Booming Worldwide | Diester Industries, Neste Oil Rotterdam, …
AMA Research released the latest research publication on Global Bioenergy market that provides up-to-date and peer-reviewed facts, figures and analysis of global developments in technology, policies, and markets. The survey with Bioenergy manufacturers and stakeholders from key geographies, reveals various challenges with regulation, development, and growth scenarios. Additionally stream of Bioenergy M&A activity and growth, as producers strive to stay ahead of the curve. Some of the players…
Research Now hires Kerem Köksal to manage new Dutch office in Rotterdam
Research Now, the leading global online sampling and data collection company, today announced the appointment of Kerem Köksal and the opening of the company’s twenty-fourth office in Rotterdam, Netherlands.
Appointed Client Development Manager Benelux, Kerem is responsible for establishing and growing the client development team in Belgium, the Netherlands and Luxembourg, and further driving business development in the surrounding region.
Kerem brings over five years of international account management experience specifically…
Rotterdam Photographer Captures Time in Motion
Rotterdam photographer Armand Dijcks announces the launch of "Lightscapes", a series of Intentional Camera Movement (ICM) photographs. "Lightscapes" literally captures time in motion as images — of a chair, kitchen mixer or piece of clothing — are transformed into something unexpected during photographing.
Curiosity led Dijcks to try several techniques before he learned about ICM photography, a technique through which images can be composed by intentionally moving the camera in all…