The European Court of Justice, Luxembourg – Formwork and protection panel climbing in weekly cycles

The combination of PERI ACS self-climbing formwork and RCS climbing protection panel provided site personnel the highest levels of safety.

The combination of PERI ACS self-climbing formwork and RCS climbing protection panel provided site personnel the highest levels of safety.

High safety requirements cost-effectively fulfilled

The European Court of Justice is the judicial branch of the European Union and is based in Luxembourg. Since 1973, a number of extension measures have had to be carried out. In the fourth and most extensive development section - which became necessary due to the admission of new EU member states from Eastern Europe - another 50,000 m² of office space has to be created. In each case, 27 floors are accommodated in the 106 m high twin towers.

PERI engineers from the Weissenhorn-based formwork and scaffolding manufacturer developed a comprehensive customized formwork solution taking into account the high safety requirements along with exact needs of the contractor. For both multi-storey buildings, the PERI ACS self-climbing formwork together with the RCS climbing protection panel offers maximum safety and efficient operational sequences. Even with high wind speeds, floors can be constructed with concreting cycle heights of 3.80 m in regular week cycles.

Each tower, with a ground plan area of 14 x 48 metres, has two different arrangements of integrated stair and elevator cores. For their construction, altogether 1,760 m² of PERI VARIO GT 24 girder wall formwork is being climbed with the help of the ACS self-climbing system in accordance with the planned weekly cycle. The combination of three versions of the modular ACS system provide an optimal operating sequence. Even the formwork for the intermediate walls and the placing boom can be comfortably integrated into the climbing units. The ACS 100 climbing mechanism, the core element of the modular PERI ACS system, brings the platforms together with the formwork smoothly up to the next section - and without the need of a crane. This means the crane is freed up for the reinforcement work and for forming the in-situ concrete slabs.

Subsequent work on the office floors can be carried out also at great heights in absolute safety and more efficiently due to the protection provided by the RCS climbing protection panel. Then the RCS completely encloses the slab edges and provides site personnel effective protection against falling. At the same time, work can still carried out efficiently even in extreme weather conditions and high wind velocities. The closed protection panel accelerates the moving of the slab formwork and gives an increased feeling of safety – this clearly boosts productivity. In addition, hinged cover boards prevent tools or materials from falling to the ground. To bolster maximum construction progress, the facade cladding for the lower floors can be safely installed at the same time as carrying out work on the concrete frame.

Shuttering, reinforcement work and striking operations for the floor slabs can be accomplished on several storeys at the same time regardless of wind and weather. The lightweight aluminium PERI SKYDECK panel slab formwork means non-tiring working conditions for construction crews with no element weighing more than 15 kg. And the SKYDECK drophead system allows early striking to take place so that panels and main beams are free to be used for the next floor area after only two days. On the one hand, this accelerates the operating sequence whilst reducing on-site material requirements on the other.

Supplemented by PERI TRIO panel formwork for forming the reinforced concrete columns, the floors of both tower blocks can be completed in the regular week cycles. Above all, for Luxembourg-based contractors, Kurt, the collective safety of the ACS and RCS climbing systems are of great importance. Moreover, through the professional PERI formwork planning, the selected systems could be closely co-ordinated and matched exactly to the construction progress.

Project data
Contractor: KURT Constructions S.A., Bridel, Luxembourg
Field Service: PERI Londerzeel, Belgium and PERI Weissenhorn, Germany

PERI was founded in 1969 and is today one of the leading providers of formwork and scaffolding systems. Along with the headquarters in Weißenhorn, Germany, the company has 45 international subsidiaries and 100 stock yards around the world. The company has over 4.500 employees of which 850 are engineers. 2006 revenues was around 920 million Euros.

PERI GmbH
Formwork, Scaffolding, Engineering
P.O. Box 1264
89259 Weissenhorn
Tel.: 49/ 73 09/ 9 50-0
Fax: 49/ 73 09/ 9 51-0
info@peri.de
www.peri.de

Re-prints are free of charge quoting "Source: PERI GmbH".
http://www.peri.de/ww/en/pub/presse/apr_01_07.cfm
Please send a copy to the PERI Editorial Office.

PERI Editorial Team
Tel.: 49/ 73 09/ 9 50-1 18
Fax: 49/ 73 09/ 9 51-1 18
redaktion@peri.de

This release was published on openPR.

Permanent link to this press release:

Copy
Please set a link in the press area of your homepage to this press release on openPR. openPR disclaims liability for any content contained in this release.

You can edit or delete your press release The European Court of Justice, Luxembourg – Formwork and protection panel climbing in weekly cycles here

News-ID: 17798 • Views:

More Releases from PERI GmbH - Formwork, Scaffolding, Engineering

Formwork and scaffolding from one source for Berlin´s City Palace
Formwork and scaffolding from one source for Berlin´s City Palace
Sep 1, 2015 - "Humboldt Forum" City Palace, Berlin For the reconstruction of Berlin´s City Palace, PERI supplied cost-effective formwork and scaffolding solutions from one source. In addition to providing large quantities of wall, column and slab formwork with fast shuttering and moving times as well as flexibly used scaffolding materials, the on-site support provided by the PERI engineers ensured that all requirements could be fulfilled along with maintaining the tight
Construction time optimisation through comprehensive working safety and crane-independent climbing
Construction time optimisation through comprehensive working safety and crane-in …
Aug 3, 2015 - International Towers Sydney ITS, Barangaroo South, Sydney, Australia The new LPS climbing protection panel from PERI provides comprehensive working safety and saves valuable crane time thanks to the mobile climbing hydraulics. This has accelerated construction progress on the International Towers Sydney complex on Australia's east coast. With the ambitious Barangaroo Redevelopment Project, Sydney's city centre is being redefined in a westward direction. On the 22-hectare former container port
System-based project solution saves time and money
System-based project solution saves time and money
July 1, 2014 - Capitol Hill Station, Seattle, USA The formwork and scaffolding solution provided for the construction of the new subway station in Seattle was the result of competent engineering and a project-specific construction kit system. In addition to the widest possible use of rentable PERI system components, the optimized construction method in particular ensured significant time and cost savings. The length of Seattle´s metropolitan railway system (Light Rail) is currently
Formwork in every shape and dimension – even faster with the new CNC system
Formwork in every shape and dimension – even faster with the new CNC system
June 16, 2014 - Visions of architects take shape with PERI Planned, formed, concreted – it is actually hard to believe that this procedure could ever function trouble-free in some cases of present-day abstract concrete structures. In its pursuit of uniqueness, architecture is becoming more and more ambitious. Parallel to this, the requirements of construction companies are likewise increasing. PERI, however, is keeping pace with this trend: with individual formwork solutions,

All 5 Releases


More Releases for ACS

IT Outsourcing Market Is Booming Worldwide | Cognizant, TCS, Sodexo, ACS
Latest added Global IT Outsourcing Market research study by HTF MI offers detailed product outlook and elaborates market review till 2026. The market Study is segmented by key regions that is accelerating the marketization. At present, the market is sharping its presence and some of the key players in the study are Accenture, HCL Technologies, HPE, IBM, TCS, Oracle, Cognizant, Infosys, CapGemini, NTT Data, Sodexo, ACS & ISS etc. The
ACS Grade Lithium Carbonate Market Size, Share, Development by 2025
LP INFORMATION recently released a research report on the ACS Grade Lithium Carbonate analysis, which studies the ACS Grade Lithium Carbonate industry coverage, current market competitive status, and market outlook and forecast by 2025. Global “ACS Grade Lithium Carbonate Market 2020-2025” Research Report categorizes the global ACS Grade Lithium Carbonate by key players, product type, applications and regions,etc. The report also covers the latest industry data,
ACS Bathrooms Fortitude Valley
ACS Designer Bathrooms, we are committed to excellence, and this commitment is evident in every single product that we sell. We offer a broad range of high-quality bath and kitchen products that will elevate the look of your home, giving it elegance and a sense of luxury in every room. ACS Designer Bathrooms, we are committed to excellence, and this commitment is evident in every single product that we sell. We
Specialty Trade Contractors Market Size, Share, Growth Analysis 2018-2023 with T …
The specialty construction contractor industry includes establishments involved in performing specific activities such as pouring concrete, site preparation, plumbing, painting and electrical work related to construction of buildings. These establishments are not responsible for an entire construction project but perform activities such as new work, additions, alterations, maintenance and repairs on a contractual basis for the main builder or owner. Get Sample Copy of this Report @ https://www.orianresearch.com/request-sample/681923 . Specialty
Air Conditioning Systems Market - Split ACs Witness Highest Demand
The vendor landscape of the global air conditioning systems market is speckled with large and established companies such as Gree Electric Appliances, Inc., Daikin Industries Ltd., and Carrier Corporation; emerging players such as Panasonic Corporation, Mitsubishi Corporation, and The Midea Group; and promising vendors such as LG Electronics, Haier Electronics Group Co., Ltd., and Hitachi Ltd. Each of these players have been striving to strengthen their position in the air
Graphene Oxide Market 2017- Angstron Materials, Graphenea,Garmor,ACS Material
The Global Graphene Oxide Market 2017 Industry Research Report focused on major manufacturers, regions, type as well as application of the Graphene Oxide industry. “””Graphene, a multi or single layer sheet of graphite, is the strongest material available, as well as being highly transparent, flexible, and the best conductor of heat and electricity. Great effort is devoted to developing an effective yet inexpensive way to produce graphene materials in industrial