May 5, 2014 - Munich Airport Satellite Terminal, GermanyIn order to be able to handle around 11 million additional passengers per year from 2015 onwards, Terminal 2 at Munich Airport is currently being expanded in the form of a satellite terminal. The fact that the new building has to be constructed during normal operations, presents great challenges for the contractor. PERI has supplied a complete solution consisting of formwork, scaffolding and engineering – and convinced both the construction company and the scaffolding contractor with its safer and faster system technology as well as a customized package of services.
Carrying out construction work while taxiing operations are proceeding as usual is a major challenge for the site personnel – this is especially true for the satellite terminal at Munich Airport, which disposes a launch capacity of 90 aircraft movements. In addition to this, the new satellite building encloses the apron tower and incorporates the existing baggage sorting centre which must be completely accessible at all times. An absolute priority is to ensure that the entire airport operations remain unaffected while, at the same time, complying with the high level of security measures.
So as to meet all the requirements of the clients, a PERI UP scaffolding completely shielded the construction site from the airport operations. Apart from the cleverly devised scaffolding construction, which also serves as a working scaffold for the facade contractors, PERI has provided a comprehensive shoring solution along with formwork technology.
The composite steel construction for the satellite terminal is being realised by Hochtief Solutions AG of Hannover. Hollow and box profiles made of steel are used as supporting, main and secondary beams, with trapezoidal sheeting as slab basic elements. Assembly of the steel construction takes place in sections with a grid dimensions of 8 m x 12 m. Around 4,500 MULTIPROP Slab Props MP 625 carry the steel skeleton when assembled until the concrete that has been placed has hardened. Thanks to their low individual weight of only 35 kg, the aluminum props can easily be handled manually – although with the enormous extension length of 6.25 m they carry up to 5.8 t.
In addition, PERI UP modular scaffolding is being used as shoring in other areas. The scaffold features 25 cm grid dimensions and consistently adapts to the range of different loads; the supporting construction meets project demands through optimized material requirements. Rapid assembly and universal utilisation possibilities, together with the high level of work safety, are the decisive advantages for the construction team.
Apart from the use of the proven TRIO panel formwork, the PERI project manager enhanced the overall solution in particular by ensuring on-schedule planning and punctual deliveries of materials which are then continuously and flexibly adapted to suit the actual construction process.
A more than 600 m long, 21 m high scaffold construction provides a reliable, hermetic separation of the construction site from the airfield. PERI specialists fulfilled the strict planning and static specifications by means of a comprehensive planning process.
Taking into consideration all stages of construction and other boundary conditions, PERI design engineers planned 7 m wide bridging in order to provide protection for baggage transport operations taking place directly underneath as well as scaffolding anchors with 6 m distance to the steel construction. RCS climbing rails from the VARIOKIT engineering construction kit and push-pull props from the accessory product range were ideally integrated into the scaffolding concept. The PERI solution also includes all technical documentation as well as all required static calculations.
In addition to this comprehensive solution, that perfectly fulfils all project requirements, PERI scaffolding technology also provides safety and assembly advantages. Thus, design details, such as the integrated protection against lifting and gap-free decking surfaces in all areas, support the fast assembly procedure through the team from scaffolding contractor Gloser.
Opened in 2003, Terminal 2 at Munich Airport handles around 25 million passengers annually. Since this nominal capacity limit no longer meets the demands, further expansion of the infrastructure is necessary. Currently, the complex is being extended through the construction of a satellite terminal which is scheduled for completion of construction in 2015. With 52 gates, 39 passenger boarding bridges and 27 aircraft stands positioned close to the building, the new structure will create the capacity to handle an additional eleven million passengers a year.
The over 600 m long and up to 80 m wide new airport building is connected via an underground automated people mover (APM) system to Terminal 2. As a landside connection is missing, the new development is considered as an extension to the existing terminal. All extension and conversion work is being carried out during daily airport operations. Airport operator FMG and Lufthansa are realizing the project together, with a total investment amounting to 650 million euros.
PERI was founded in 1969 and is today the leading provider of formwork and scaffolding systems. Along with the headquarters in Weissenhorn, Germany, the company has more than 50 international subsidiaries and 110 stock yards around the world. The company has over 6,700 employees. 2013 revenues was 1,099 million Euros.
PERI GmbH
Editorial Office
P.O. Box 1264
89259 Weissenhorn
Germany
Phone: +49 (0) 7309.950-1191
Fax: +49 (0) 7309.951-1191
E-Mail: redaktion@peri.de
Web: www.peri.com
Re-prints are free of charge quoting "Source: PERI GmbH". Please send a copy to the PERI Editorial Office.
This release was published on openPR.
Permanent link to this press release:
Copy
Please set a link in the press area of your homepage to this press release on openPR. openPR disclaims liability for any content contained in this release.
You can edit or delete your press release Comprehensive range of services for construction and scaffolding companies here
News-ID: 287659 • Views: …
More Releases from PERI GmbH

Supporting system solution – individually adapted
December 3, 2012 - Motorway Bridge T4, Paradisia-Tsakona, Greece
A huge inclined pier supports the motorway bridge on the Greek peninsula of Peloponnese. A team of Greek and German PERI engineers are supporting the site management team with project-specific system solutions.
The 160-km long A7 motorway connects Kalamata in the south to Corinth in the northwest of the Peloponnese peninsula. The principle element being used to close the gap between Paradisia…
More Releases for Munich
Transcendent Couple's Time in Wintry Munich
The English Garden, resplendent in its dazzling, white splendor. The bone-chillingly cold Isar River, transforming into an ice-lover's sanctuary. Countless Christmas markets, wafting fragrant aromas of myriad spices through the crisp winter air...
While the time-honored city escapade is typically reserved for the warmer seasons, one can experience a truly enchanting time in Munich, particularly during the wintry months. This is especially true when visiting as a couple and choosing the…
RTI: Munich Connext Conference 2019
SUNNYVALE (USA)/London, February, 2019 – Interested in designing smarter and more secure systems that connect the IIoT? Real-Time Innovations (RTI) is bringing its annual EMEA Connext Conference to Munich, Germany (May 21-22, 2019). Users, developers and industry partners learn the latest in technical information and developer experiences in building real-world IIoT systems.
The internet has evolved from connecting people to devices, to connecting devices to devices and systems to systems. And…
DevOpsCon Munich is getting closer!
Modern DevOps does more than just bringing together Devs and Ops. It aims to integrate business and IT across teams and systems. This is the mission of DevOpsCon - the conference for agile processes, microservices, continuous delivery, container and cloud technologies. These topics are essential to the current high-performance IT transformation and that's the reason why DevOpsCon is always a good place for learning and connecting.
The conference's robust program…
HOCHTIEF Projektentwicklung sells smarthouse in Munich
Competo Capital Partners acquires office and commercial building for investor consortium
HOCHTIEF Projektentwicklung has sold the smarthouse in Munich to Competo Capital Partners. The real estate company acquired the office and commercial building which was completed in 2012 for the “Competo BestandPlus” investor consortium that it represents. It was agreed that the purchase price would not be disclosed. Around 90 percent of the seven-story smarthouse’s 22,000 square meters are let.
Apart from…
Sightrunning in Munich: Cultural Tour at the MUNICH MARATHON
To discover a metropolis in an active way with running shoes instead of sitting in crowded travel busses is no insider’s tip anymore. If the route not only leads along important sights, but also offers the opportunity to enjoy the view together with many like-minded people, unforgettable moments are guaranteed. On October 13th 2013, the MUNICH MARATHON promises sightrunning on a high cultural level.
The course through Bavaria’s capital displays the…
HALCON 10 Distributor Training in Munich
Regarding the launch of the new version 10 of their machine vision software HALCON, MVTec Software GmbH held an international distributor training in Munich, Germany, from September 27 to October 01, 2010. HALCON 10 will be available via MVTec’s global distribution network from October 10, 2010.
50 sales engineers from 20 countries over the world took part in this event. In North America, a separate distributor training will take place. Topics…