openPR Logo
Press release

System-based project solution saves time and money

The VARIOKIT formwork carriage ensured rapid concreting sequences for the construction of the new subway station in Seattle.

The VARIOKIT formwork carriage ensured rapid concreting sequences for the construction of the new subway station in Seattle.

July 1, 2014 - Capitol Hill Station, Seattle, USA

The formwork and scaffolding solution provided for the construction of the new subway station in Seattle was the result of competent engineering and a project-specific construction kit system. In addition to the widest possible use of rentable PERI system components, the optimized construction method in particular ensured significant time and cost savings.

The length of Seattle´s metropolitan railway system (Light Rail) is currently being extended by 5 km and includes increasing the number of stations from 18 to 20 – as part of the rapid transit project for the Greater Seattle region. Capitol Hill, one of the two new subway stations is around 100 m long and is being realized at a depth of 18 m. Huge steel-composite tubes with 1.00 m and 1.50 m diameters respectively brace the underground structure on two levels.

Engineering with system

A very experienced team of PERI engineers from PERI USA and PERI Germany developed a cost-effective solution for this project. Economical due to the fact that, on the one hand, the walls and reinforced concrete beams could be monolithically constructed, i.e. concreted in one pour, thus avoiding the need for construction joints as well as resulting in assembly cost savings. On the other, the PERI solution is largely based on the VARIOKIT engineering construction kit with rentable system components which are available at very short notice. For Turner Construction´s site management team this has meant tremendous time and cost savings for the realization of the ambitious building project.

One formwork carriage for three tunnel levels

The VARIOKIT formwork carriage construction for the nine deepest sections, each 12 m long and 8 m high, has been designed with two parts. As a result, it has also been possible to use the top half of the carriage for the remaining two levels after completion of the lower level. These were realized using 6 concreting cycles each time with heights of 5 m and 4 m respectively.

The PERI formwork carriage is fully hydraulically operated, and moved along on the reinforced concrete edge beams of the respective lower level by means of heavy duty rollers. HD 200 heavy-duty props were used here as temporary supports for the edge beams in order to safely transfer the additional loads from the formwork carriage and the respective concreting cycle. Furthermore, the VARIOKIT unit served to support the huge steel tubes so that it was also possible to fill these with concrete at the same time as the walls were being concreted.

In order to transfer the high loads resulting from the concreting operations for the 1.22 m thick reinforced concrete slab of the subway station into the longitudinal edge beams, the formwork carriage was adapted to suit the changed load situation. However, the VARIOKIT system components as well as the hydraulic handling and easy movability of the complete formwork carriage unit continued to be used.

Comprehensive: system and detailed solutions

Contributing positively to ensure the project was successfully realized was the fact that the PERI project team were also able to develop, in particular, detailed solutions for all stages of construction: for example, the design of the widened areas along the bottom level and the positioning of the steel tubes below a temporary bridge. Here, the VARIOKIT formwork carriage likewise served as a transport vehicle. In addition, the PERI systems TRIO, VARIO GT 24, SB Brace Frames, MULTIFLEX, MULTIPROP shoring towers and PERI UP stair access complemented the comprehensive project solution.

VARIOKIT engineering construction kit

With standardized, rentable system components and site-compliant connecting means of the VARIOKIT engineering construction kit, bridge and tunnel structures can be cost-effectively realized and optimally adapted to suit the respective construction requirements. Furthermore, the modular design allows customized, load-optimized supporting formwork solutions for virtually all geometries.

Seattle

Seattle is the largest city in the north-west of the USA, and home to such well-known companies as Microsoft, Amazon, Boeing and Starbucks. For movie and television audiences, the city is known for films like "Sleepless in Seattle" or the TV series "Grey's Anatomy".

PERI was founded in 1969 and is today one of the leading providers of formwork and scaffolding systems. Along with the headquarters in Weissenhorn, Germany, the company has more than 50 international subsidiaries and over 100 stock yards around the world. The company has over 6700 employees. 2013 revenues was 1,099 million Euros.

PERI GmbH
Editorial Office
P.O. Box 1264
89259 Weissenhorn
Germany

Phone: +49 (0) 7309.950-1191
Fax: +49 (0) 7309.951-1191
E-Mail: redaktion@peri.de
Web: www.peri.com

Re-prints are free of charge quoting "Source: PERI GmbH". Please send a copy to the PERI Editorial Office.

This release was published on openPR.

Permanent link to this press release:

Copy
Please set a link in the press area of your homepage to this press release on openPR. openPR disclaims liability for any content contained in this release.

You can edit or delete your press release System-based project solution saves time and money here

News-ID: 290896 • Views:

More Releases from PERI GmbH - Formwork, Scaffolding, Engineering

Formwork and scaffolding from one source for Berlin´s City Palace
Formwork and scaffolding from one source for Berlin´s City Palace
Sep 1, 2015 - "Humboldt Forum" City Palace, Berlin For the reconstruction of Berlin´s City Palace, PERI supplied cost-effective formwork and scaffolding solutions from one source. In addition to providing large quantities of wall, column and slab formwork with fast shuttering and moving times as well as flexibly used scaffolding materials, the on-site support provided by the PERI engineers ensured that all requirements could be fulfilled along with maintaining the tight
Construction time optimisation through comprehensive working safety and crane-independent climbing
Construction time optimisation through comprehensive working safety and crane-in …
Aug 3, 2015 - International Towers Sydney ITS, Barangaroo South, Sydney, Australia The new LPS climbing protection panel from PERI provides comprehensive working safety and saves valuable crane time thanks to the mobile climbing hydraulics. This has accelerated construction progress on the International Towers Sydney complex on Australia's east coast. With the ambitious Barangaroo Redevelopment Project, Sydney's city centre is being redefined in a westward direction. On the 22-hectare former container port
Formwork in every shape and dimension – even faster with the new CNC system
Formwork in every shape and dimension – even faster with the new CNC system
June 16, 2014 - Visions of architects take shape with PERI Planned, formed, concreted – it is actually hard to believe that this procedure could ever function trouble-free in some cases of present-day abstract concrete structures. In its pursuit of uniqueness, architecture is becoming more and more ambitious. Parallel to this, the requirements of construction companies are likewise increasing. PERI, however, is keeping pace with this trend: with individual formwork solutions,
Test of strength for PERI formwork and scaffolding
Test of strength for PERI formwork and scaffolding
June 3, 2014 - Stanari Thermal Power Station, Doboj, Bosnia-Herzegovina he Energy Financing Team (EFT) is currently constructing the Stanari coal powered power plant near Doboj. For this project, the contractors have been tasked to realize a particularly large scale, massive structure whilst, at the same time, complying with small dimensional tolerances. PERI supplies two of the building contractors involved with a customized formwork and scaffolding solution. In addition to the

All 5 Releases


More Releases for VARIO

Alti-Vario-GPS Market To Witness Huge Growth By 2027- Charly Produkte, Compass, …
Complete study of the global Alti-Vario-GPS market is carried out by the analysts in this report, taking into consideration key factors like drivers, challenges, recent trends, opportunities, advancements, and competitive landscape. This report offers a clear understanding of the present as well as future scenario of the global Alti-Vario-GPS industry. Research techniques like PESTLE and Porter's Five Forces analysis have been deployed by the researchers. They have also provided accurate
Alti-Vario-GPS Market Challenges on Upcoming Trends 2026
How The Alti-Vario-GPS Market Will Behave? Latest research report on the Alti-Vario-GPS Market published. This is a key document as far as the clients and industries are concerned to not only understand the competitive market status that exists currently but also what future holds for it in the upcoming period, i.e., between 2020 and 2026. It has taken the previous market status of 2015 – 2019 to project the future status. The report
Alti-Vario-GPS Market Report, History and Forecast 2020-2026|Compass, Digifly, F …
In a recent study published by QY Research, titled "Global Alti-Vario-GPS Market Research Report", analysts offer an in-depth analysis of the global Alti-Vario-GPS market. The study analyzes the various aspects of the market by studying its historic and forecast data. The research report provides a Porters five force model, SWOT analysis, and PESTEL analysis of the Alti-Vario-GPS market. The different areas covered in the report are Alti-Vario-GPS market size, drivers
Alti-Vario-GPS Industry Value and Volume 2018 with Status and Prospect to 2025
This report presents the worldwide Alti-Vario-GPS market size (value, production and consumption), splits the breakdown (data status 2013-2018 and forecast to 2025), by manufacturers, region, type and application. This study also analyzes the market status, market share, growth rate, future trends, market drivers, opportunities and challenges, risks and entry barriers, sales channels, distributors and Porter's Five Forces Analysis. Get to know more about Alti-Vario-GPS Market Insights, Forecast to 2025 research report
Alti-Vario-GPS Industry Value and Volume 2018 with Status and Prospect to 2025
This report presents the worldwide Alti-Vario-GPS market size (value, production and consumption), splits the breakdown (data status 2013-2018 and forecast to 2025), by manufacturers, region, type and application. This study also analyzes the market status, market share, growth rate, future trends, market drivers, opportunities and challenges, risks and entry barriers, sales channels, distributors and Porter's Five Forces Analysis. The Alti-Vario-GPS market was valued at Million US$ in 2017 and is projected to
Global Alti-Vario-GPS Market 2017 Share, Trend, Segmentation and Forecast to 202 …
Global Alti-Vario-GPS Industry Latest Report on Alti-Vario-GPS Market Global Analysis & 2022 Forecast Research Study Geographically, this report is segmented into several key Regions, with production, consumption, revenue (million USD), market share and growth rate of Alti-Vario-GPS in these regions, from 2012 to 2022 (forecast), covering North America Europe China Japan Southeast Asia India Global Alti-Vario-GPS market competition by top manufacturers, with production, price, revenue (value) and market share for each manufacturer; the top players including Charly Produkte Compass Digifly Flymaster Avionics FLYNET Flytec Renschler REVERSALE SkyBean Skytraxx STODEUS Syride XC Tracer Try